Deep Yellow Limited (DYLLF) June 2024 Quarterly Activities Report

Deep Yellow Limited (ASX:DYL) (FRA:JMI) (OTCMKTS:DYLLF) is pleased to provide a summary of key activities completed in the June 2024 quarter.
Tumas Project
- Ausenco Services Pty Ltd selected as preferred EPCM contractor for the flagship Tumas Project
o Scope of work to be completed includes finalising detailed engineering with an EPCM contract opportunity for project execution
o Project remains scheduled for commissioning Q3 2026
- Resource upgrade drilling at Tumas 3 completed with data preparation underway for release of updated Mineral Resource Estimate early August
- Post Quarter - Nedbank Limited mandated as lead arranger and bookrunner for project financing
Mulga Rock Project
- Hydrological drilling program commenced to define water management parameters for mining
- Several remaining evaluation programs underway, results to be key inputs for the revised DFS
o Resin pilot program commenced for optimisation of uranium and critical minerals extraction
o Mining study underway to determine optimal method for development of the multi-commodity mining operation and revised Ore Reserve Estimate
Corporate
- Deep Yellow enters the S&P/ASX 200 Index
- Successful A$250M capital raising completed
- Cash position - A$257.5M
*To view the full quarterly report with tables and figures, please visit:
https://abnnewswire.net/lnk/D8BLH388
John Borshoff Managing Director/CEO T: +61-8-9286-6999 E: john.borshoff@deepyellow.com.au W: www.deepyellow.com.au Media: Cameron Gilenko T: +61-466-984-953 e: cgilenko@citadelmagnus.com
News Provided by ABN Newswire
Cultivating Smart Saving Habits