i-80 Gold Reports Fourth Quarter and Full Year 2024 Operating and Financial Results
i-80 Gold Reports Fourth Quarter and Full Year 2024 Operating and Financial Results |
[31-March-2025] |
Ongoing Focus on Granite Creek Underground Ramp-Up, Balance Sheet Strengthening, and Advancing Pipeline of Projects Towards Feasibility RENO, Nev., March 31, 2025 /PRNewswire/ - i-80 GOLD CORP. (TSX: IAU) (NYSE American: IAUX) ("i-80 Gold", or the "Company") reports its operating and financial results for the fourth quarter and full year ended December 31, 2024, and provides an update on recent recapitalization initiatives, including a new gold and silver prepay agreement entered into with National Bank of Canada ("National Bank"). Unless otherwise stated, all amounts referred to herein are in U.S. dollars (C$ represents Canadian dollars). "2024 ended with a pivotal shift as we established a new development plan and commenced the work to release updated Preliminary Economic Assessments ("PEA") for each of our five gold projects, which we released as planned in the first quarter of this year," stated Richard Young, Chief Executive Officer. "These PEAs represent solid base case scenarios, and we believe the economics will continue to improve as we advance each project toward feasibility. Our focus remains on the continued ramp up at our Granite Creek Underground Project, unlocking the full potential of our portfolio, and strengthening our balance sheet to support our growth strategy. To that end, we are very pleased to have entered into an agreement with National Bank to term out the Company's gold and silver prepays due in March, and we look forward to a continued partnership with them." OPERATING AND FINANCIAL HIGHLIGHTS Fourth Quarter 2024
Year ended December 31, 2024
STRATEGY OVERVIEW Following a leadership change, the Company adopted a new development plan in the fourth quarter which presents a new view on the most effective strategy to generate free cash flow, while progressing earlier stage projects to provide a pipeline of growth over the medium and long-term. Management is now focused on permitting and developing its portfolio of assets through the balance of the decade. Consistent with i-80 Gold's focus since inception, this plan includes the development of the three underground mines but also includes accelerating, permitting, and the development of two large oxide open pit deposits, one at Granite Creek and the other at Mineral Point, within the Ruby Hill Project area. The Lone Tree Autoclave remains as the centralized refractory mineral processing facility in the new development plan in support of i-80 Gold's hub-and-spoke regional mining and processing strategy. Management intends to continue its work towards completion of the refurbishment feasibility study planned in 2025. In support of the new development plan, the Company has initiated a recapitalization plan of its balance sheet. OUTLOOK AND RECAPITALIZATION UPDATE The Company expects to produce between 30,000 to 40,000 ounces1 of gold in 2025. Production from Granite Creek underground is expected to range between 20,000 to 30,000 ounces1 of gold, and the Company's two residual heap leach operations are expected to contribute approximately 10,000 ounces of gold in 2025. The PEAs covering the Company's five gold projects were filed in March 2025, and outline three areas of growth expenditure over the next three years to support the advancement of the Company's development plan. These growth expenditures which are discretionary and subject to available resources, ranked from highest priority are: (i) advancing permitting activities, (ii) feasibility studies, and (iii) development work at Archimedes underground. For 2025, the growth expenditures are expected to total between $40 million to $50 million. Management is advancing its recapitalization plan to support the Company's development plan on several fronts, and is in active discussions with several parties regarding a number of financing options including a senior lending facility, royalty sales, non-core asset sales (such as its FAD property), a working capital facility, as well as terming out the 2025 quarterly gold prepays. Further to the recapitalization plan, the Company restructured its March 31, 2025, gold prepay and silver deliveries and entered into a working capital facility, as described herein. This outlook, including expected results and targets, is subject to various risks, uncertainties and assumptions, which may impact future performance and the Company's ability to achieve the results and targets discussed in this section. Please refer to "Forward Looking Information" section. The Company may update this outlook depending on changes in metal prices and other factors. New Gold & Silver Prepay Agreement & Working Capital Facility On March 31, 2025 the Company entered into a new gold and silver prepay arrangement with National Bank of Canada ("National Bank") under which National Bank purchased approximately 6,800 ounces of gold and 345,000 ounces of silver from the Company for delivery to National Bank by September 30, 2025 or earlier, upon an infusion of capital in line with the recapitalization plan. The proceeds of this new prepay arrangement will be used to satisfy the March 31, 2025 gold and silver deliveries due to an affiliate of Orion Mine Finance under its respective Gold Prepay and Silver Purchase and sale agreements. The obligations under the prepay arrangement with National Bank are secured by the FAD project. In addition, the Company is finalizing a working capital facility with Auramet International, Inc. for up to $12 million, maturing in 12 months.
OPERATIONAL AND FINANCIAL OVERVIEW
Granite Creek Underground
Mining rates and gold extraction for the year 2024 were below the anticipated levels due to an escalation in groundwater ingress into the underground working areas. This development adversely affected productivity and the pace of development. In response to the increased water ingress, the mine expanded pumping capacity, deepened an existing dewatering well, drilled a new dewatering well, and reconfigured the dewatering system to enhance the flow capacity to the water treatment facility. Water levels are dropping throughout the mining area and water ingress rates are anticipated to decrease in the near term. extraction rates are expected to ramp up to steady-state during the second half of 2025. Additional dewatering infrastructure upgrades will be completed in 2025. In early 2025 a predictive groundwater model was completed and the Company is utilizing this study to evaluate future dewatering needs. The Company continues to encounter elevated levels of oxide mineralized material. A substantial portion of this lower-grade mineralized material has been deemed suitable for processing via heap leach at the Company's Lone Tree heap leach facility. During the quarter, 1,261 ounces were processed and sold from the Lone Tree heap leach facility. Additionally, during the three months ended in December 31, 2024, 30,911 tonnes of sulfide mineralized material were processed under the toll milling agreement. As at December 31, 2024, sulfide mineralized material of approximately 13,000 tonnes were on the stockpile to be processed in 2025. Capital expenditures for the year were primarily related to mining equipment. Pre-development expenditures are for underground development work, definition drilling and dewatering well costs. During the fourth quarter, Management began a process to update the technical reports for both the Granite Creek underground and open pit projects which were completed during the first quarter of 2025. An infill drilling program is planned to be completed in 2025 to upgrade resources to a feasibility study level. Permitting activities associated with the Granite Creek open pit expansion are planned to begin in early 2025 with the initial focus on required baseline field studies. Federal National Environmental Policy Act ("NEPA") and State of Nevada permitting is anticipated to take approximately three years. During the three months ended December 31, 2024, the Company paused its drilling program in favor of developing an underground exploration drift. The development of an exploration drift at Granite Creek Underground commenced in the fourth quarter of 2024. This drift will provide access for infill drilling from underground in the South Pacific Zone. Ruby Hill (Archimedes Underground Project and Mineral Point Open Pit Project)
During the three and twelve months ended December 31, 2024, the Company continued to recover ounces from the heap leach pads at Ruby Hill. The volume of ounces sold was lower than the prior year comparable periods due to the continued decline in leachable ounces. The Company will continue to recover ounces from the leach pads at Ruby Hill as long as it is economical to do so. There was minimal spending on capital expenditures for the three and twelve months. During the fourth quarter, the Company prepared a preliminary economic assessment on the Archimedes Underground Project and Mineral Point open pit project which was finalized in the first quarter of 2025. Exploration spending for the three and twelve months were related to metallurgical tests and drilling for metallurgical samples on the base metal deposits. Permitting for Archimedes underground continued in the fourth quarter of 2024. During the first quarter of 2025 the Company received the record of decision from the U.S. Bureau of Land Management for the commencement of the underground portals. Associated state permits are still in process and are expected to be received in the second quarter of 2025. Construction of the surface facilities and associated infrastructure commenced in the fourth quarter of 2024 and will carry into the first half of 2025. Underground construction activities are expected to begin in the third quarter of 2025. The Mineral Point deposit drill program is expected to begin in the third quarter of 2025 to support geotechnical, metallurgical and hydrology studies for baseline data to advance the permitting and technical reports for Mineral Point. Permitting and technical study advancement of the base metal deposits at Ruby Hill including Hilltop and Blackjack have been suspended for the foreseeable future as the Company focuses on ramping up, permitting and developing the Company's three underground and two open pit oxide gold projects through the balance of the decade. As a result of the adoption of the new gold-focused strategy, the base metal joint venture, which the Company had been advancing previously, has been terminated. Cove Project The draft plan of operations has been submitted to the U.S. Bureau of Land Management and the baseline permitting work is largely in the process of being finalized. In 2024, the Company focused on updating their existing permits related to water pollution control and land reclamation to ensure compliance with environmental regulations and maintaining operational standards. Additionally, a new air quality operating permit application will be submitted to the regulatory agency. This new permit is essential for regulating and controlling the emissions and pollutants released into the air by the site, thereby ensuring that the operations meet air quality standards set by regulatory authorities. Management is targeting the submittal of an Environmental Impact Statement in mid-2025, which will be required primarily due to significant project disturbance acres and impact on water. The preparation and submission of these permitting documents are anticipated to be a key priority in the first half of 2025.
Underground delineation drilling continued during the fourth quarter on the Helen the CSD and Gap deposits with two core rigs, completing 26,533 feet of core drilled bringing total drilling over the course of the infill campaign to approximately 78,776 feet. A further 15,000 feet of drilling is planned into the first quarter of 2025 to complete the program. The 2024/2025 drill program will be included in a planned updated feasibility study. Lone Tree The focus at Lone Tree is a feasibility study to evaluate the refurbishment of the autoclave facility with the intention of processing sulfide ore from the three underground mines (Granite Creek, Archimedes and Cove) in support of the Company's regional hub-and-spoke mining and processing strategy. Management continues to review the value engineering studies in preparation for the feasibility study which is expected to be completed in the third quarter of 2025. The Lone Tree open pit is expected to remain in inventory into the 2030's as the Company focuses ramp up, permitting and development of its three underground mines and two open pit oxide mines. At the Company's Lone Tree property, the continued leaching of the historic leach pad is producing a reasonable amount of gold. The Company plans to continue to recover ounces from the Lone Tree leach pads as long as it is economical to do so.
Capital expenditures for the three and twelve months were related to general infrastructure in sustaining the operations and activities at Lone Tree. Spending in 2023 was related to the technical work on the refurbishment of the autoclave processing plant. FINANCIAL STATEMENTS This press release should be read in conjunction with i-80 Gold's Annual Report on Form 10-K, including the audited consolidated financial statements and associated Management's Discussion and Analysis of Operations and Financial Condition for the three months and year ended December 31, 2024 included therein, which is available on the Company's website at www.i80gold.com, on EDGAR at www.sec.gov, and on SEDAR+ at www.sedarplus.ca. Transition to US Generally Accepted Accounting Principles ("US GAAP") Historically, the Company has prepared its financial statements under International Financial Reporting Standards Accounting Standards as issued by the International Accounting Standards Board ("IFRS") permitted by security regulators in Canada, as well as in the U.S. under the foreign private issuer status as defined by the United States Securities and Exchange Commission ("SEC"). On June 28, 2024, the Company determined that it would no longer qualify as a foreign private issuer under the SEC rules as of January 1, 2025. As a result, beginning January 1, 2025 the Company was required to report with the SEC on domestic forms and comply with domestic company rules. Consequently, the Company was required to prepare its financial statements using US GAAP effective beginning with the Company's 2024 annual consolidated financial statements to which this Management's Discussion and Analysis of Financial Condition and Results of Operations ("MD&A") relates and for all subsequent reporting periods. CONFERENCE CALL AND WEBCAST Management will hold a conference call and audio webcast to discuss the fourth quarter and full year results, as well as recent recapitalization efforts, followed by a question-and-answer session from participants. The details are as follows: Date: April 1, 2025 QUALIFIED PERSONS Tyler Hill, CPG-12146, VP Geology, and Tim George, PE, VP Operations, at i-80 Gold have reviewed this press release and are the Qualified Persons for the information contained herein and are a "Qualified Person" within the meaning of National Instrument ABOUT i-80 GOLD CORP. i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a new development plan to advance its high-quality asset portfolio. The Company is the fourth largest gold mineral resource holder in the state with a pipeline of high-grade development and production-stage projects strategically located in Nevada's most prolific gold-producing trends. Leveraging its fully permitted central processing facility following an anticipated refurbishment, i-80 Gold is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth. i-80 Gold's shares are listed on the Toronto Stock Exchange (TSX: IAU) and the NYSE American (NYSE: IAUX). For more information, visit www.i80gold.com. FORWARD LOOKING INFORMATION Certain information set forth in this press release including but not limited to management's assessment of the Company's future plans and operations, the perceived merit of projects or deposits, and the impact and anticipated timing of the Company's development plan and recapitalization plan, production guidance and outlook, the anticipated growth expenditures, the anticipated timing of permitting, production, project development or technical studies constitutes forward looking statements or forward-looking information within the meaning of applicable securities laws. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Readers are cautioned that the assumptions used in the preparation of information, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, reliance should not be placed on forward looking statements. The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits, if any, that the Company will derive there from. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Company's control, including general economic and industry conditions, volatility of commodity prices, title risks and uncertainties, ability to access sufficient capital from internal and external sources, the Company may be required to adopt one or more alternatives, such as selling assets, restructuring debt or obtaining additional equity capital on terms that may be onerous or highly dilutive. The Company's ability to refinance its indebtedness will depend on the capital markets and its financial condition at such time, currency fluctuations, construction and operational risks, licensing and permit requirements, environmental risks, competition from other industry participants, the lack of availability of qualified personnel or management, imprecision of mineral resource, or production estimates and stock market volatility. Please see "Risks Factors" in the Annual Report on Form 10-K for the fiscal year ended December 31, 2024 for more information regarding risks pertaining to the Company, which is available on EDGAR at www.sec.gov/edgar and SEDAR+ at www.sedarplus.ca. Readers are encouraged to carefully review these risk factors as well as the Company's other filings with the U.S. Securities and Exchange Commission and the Canadian Securities Administrators. All forward-looking statements contained in this press release speak only as of the date of this press release or as of the dates specified in such statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise except as required by applicable law. Additional information relating to i-80 Gold can be found on i-80 Gold's website at www.i80gold.com, SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov/edgar. NON-GAAP FINANCIAL PERFORMANCE MEASURES The Company has included certain terms or performance measures commonly used in the mining industry that are not defined under US GAAP in this document. This includes average realized price per ounce. Non-GAAP financial performance measures do not have any standardized meaning prescribed under US GAAP, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with US GAAP and should be read in conjunction with the Company's Financial Statements. For a more detailed breakdown on how this measure was calculated, please see the definition and table below. Definitions "Average realized gold price" per ounce of gold sold is a non-GAAP measure and does not constitute a measure recognized by US GAAP Accounting Standards and does not have a standardized meaning defined by US GAAP Accounting Standards. It may not be comparable to information in other gold producers' reports and filings. Average realized gold price per ounce of gold sold
SOURCE i-80 Gold Corp | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||