Silvercorp Announces Project Update for El Domo
Silvercorp Announces Project Update for El Domo |
| [04-February-2026] |
Trading Symbol: TSX/NYSE American: SVM VANCOUVER, BC, Feb. 4, 2026 /PRNewswire/ - Silvercorp Metals Inc. ("Silvercorp" or the "Company") (TSX/NYSE American: SVM) (the "Company") announces an update for its budget and construction schedule for the construction of the El Domo Project (the "Project"). The construction budget for the Project has been updated to $284 million, an increase of $44 million compared to the $240 million estimate dated March 31, 2025 (for reference, the 2021 Feasibility Study Budget was $248 million). The main items of increase or decrease are as follows:
Capital Cost Estimate Details:
Based on this new budget, the El Domo Project is scheduled to be in production by July 1st, 2027, representing a six-month delay from the previous estimate of early-2027. Progress Achieved in 2025: 2025 has been a productive year, as we focused on construction Package #1: including Site preparation, Roads, Non-contact Water Channels, TSF, Saprolite Waste Dump ("SWD"), and proceeded with other packages. During the year, we established a new project construction team, while overcoming an exceptionally heavy and long rainy season that lasted well into June, working with different communities and government agencies to ensure a sound working environment. Through the hard work of our local team, CRCC 14 and other contractors, along with the support of communities and government authorities, the Company made significant progress at the Project.
Bidding for the Package #2 - Open Pit Mining and Stripping After a competitive bidding process and several months of negotiation, the Company is expected to execute the mining contract for the construction and operation of the Project with China Railway 19th Bureau Group Co., Ltd. ("CRCC 19") on a "Unit Cost" basis, that is, the cost of drilling, blasting, hauling and dumping or compacting each cubic metre of rock over a certain distance. The fixed unit rate contract is structured into two primary phases: 1) the Construction Phase, valued at $35 million for mining and stripping, includes pre-stripping activities such as earthworks, rock stripping, and by-product ore mining; and 2) the Operations Phase, valued at approximately $63 million over the subsequent five years, covers annual mining and stripping of ore and waste rock. In addition, the contract includes the construction and management of the multi-stage raising of the Tailings Storage Facility (TSF) dam ($8 million). CRCC19 has a regional headquarter in Quito with over ten years operating experience in Ecuador building a large open pit copper-gold mine and ongoing mining and stripping. In advance of executing the contract CRCC 19 began mobilizing personnel to the El Domo site in January 2026 and equipment mobilization will begin this month. Package #3 - Processing plant construction and equipment Yantai Jinpeng Mining Machinery Co.,Ltd is expected to complete the detailed engineering design of the processing plant based on the new flowsheet by early April 2026. This will serve as the cost base to initiate the bidding process for construction. With most equipment already ordered, the primary budget variables for Package #3 would be the construction cost and materials Packages #4 - External Powerline and standby diesel generators The total distance of the external powerline is 61.3 km. The northern section (27.5 km) and three substations, with a $10.15 million budget, have been awarded to two Ecuadorian contractors last September, but only recently received the approval by CNEL required before construction can be started. The southern part (33.8 km) is pending the completion of detailed engineering design. The powerline is expected to be completed in 2027. As a backup plan, the company has ordered 14MW of diesel generator sets which will be delivered to site by December 2026 for installation. This mitigation plan will ensure power is available for commissioning of the process plant in July 2027, regardless of the External Powerline status. Qualified Person Guoliang Ma, P. Geo., Manager of Exploration and Resource of the Company, is the Qualified Person for Silvercorp for the purposes of National Instrument 43-101 – Standards of Disclosure for Mineral Projects (''NI 43-101'') and has reviewed and approved the technical information contained in this news release. About Silvercorp Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com. For further information Silvercorp Metals Inc. CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws relating to, among other things statements regarding the recovery of the VAT as a tax credit, the construction schedule, duration, and costs for the development of the Project, date which the Project is scheduled to be in production; timing of execution of mining contract and mobilization of personnel and equipment to the Project, timing of completion of detailed engineering design, delivery of diesel generators, and completion of powerline. By their very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance. We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including fluctuating commodity prices; recent market events and condition; activities of anti-mining groups; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders; acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment in Ecuador and China; regulatory environment and political climate in Bolivia and Ecuador; integration and operations of Adventus; environmental risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security risks; public health crises; the Company's investment in New Pacific Metals Corp. and Tincorp Metals Inc.; and the other risk factors described in the Company's Annual Information Form and other filings with Canadian and U.S. regulators on www.sedarplus.ca and www.sec.gov; could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information and that it would be unreasonable to rely on such statements as creating legal rights regarding our future results or plans. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents expectations as of the date of this news release and is subject to change after such date. However, we are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein. A comprehensive discussion of other risks that impact Silvercorp can also be found in their public reports and filings which are available under its profile at www.sedarplus.ca.
SOURCE Silvercorp Metals Inc. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||