NORTHCLIFF ANNOUNCES RESULTS OF FEASIBILITY STUDY UPDATE FOR SISSON PROJECT
NORTHCLIFF ANNOUNCES RESULTS OF FEASIBILITY STUDY UPDATE FOR SISSON PROJECT |
| [31-August-2026] |
Proposed Sisson Mine would be a key producer of critical minerals VANCOUVER, BC, Aug. 31, 2026 /CNW/ -- Northcliff Resources Ltd. ("Northcliff" or the "Company") (TSX: NCF) is pleased to announce the results of the Feasibility Study Update (the "2026 Study" or "Feasibility Study Update") for the Sisson Project ("Sisson"), located in New Brunswick ("NB"), Canada. The study forecasts strong financial results for an open pit mine and processing facility producing concentrates of tungsten and molybdenum - two critical minerals, as recognized by Canada and other international jurisdictions. All values are expressed in Canadian dollars unless otherwise noted and are presented on a 100% project basis. All tonnages are stated in metric tonnes ("t"). 2026 Feasibility Study Update Highlights
Northcliff President and CEO Andrew Ing said: "Northcliff's goal is to become a reliable and easily accessible producer of tungsten and molybdenum, increasing resiliency in the supply chain of these two critical minerals for Canada and its trading partners. The positive results of the Feasibility Study Update is a key step toward that goal." "The results of the 2026 Study reflect some significant changes in the macroeconomic environment and metal markets since the feasibility study in 2013. Metal prices, particularly for tungsten, have increased since 2013, and the change in exchange rate have improved the financial results. Increases in inflation and provincial tax rates since that time have increased capital and operating costs and income taxes. Additionally, refinements to the mine plan, tailings facility and infrastructure, primarily due to the incorporation of updated guidelines and other improvements have added to the capital and operating costs." "Current market research supports the production of tungsten concentrate rather than Ammonium Paratungstate ("APT") as was proposed in 2013, and this decrease in process plant cost has partially offset other costs. We continue, however, to assess the strategic option of producing APT based on the Project's in-hand approvals and longevity of the proposed mine vis a vis market conditions." "We look toward putting the final elements in place to accelerate the Sisson Project toward a construction decision in the latter part of 2027." 2026 Feasibility Study Update – Key Metrics
Project Sensitivities A sensitivity analysis was conducted on the base case pre-tax and post-tax NPV and internal rate of return of the project, using the following variables: commodity prices, operating costs, initial capital costs, metal recovery, head grade and exchange rate. The project is most sensitive to changes in foreign exchange rate, commodity price, head grade and recovery; it is less sensitive to total operating cost and sustaining capital cost. The post and pre-tax sensitivities for the NPV (in millions of dollars) and IRR are tabulated below:
Metal Price Environment and Current Market According to a recent 2026 Argus market study, the tungsten market has fundamentally changed, and prices are unlikely to return to historical averages. This structural change reflects both near-term and long-term demand factors. New supply capacity is expected to moderate prices, particularly outside China, but cannot restore pre-control pricing dynamics given the altered demand composition and regulatory environment. The tungsten market now exhibits a pronounced geographic division: European prices remain close to record highs while spot prices in China have fallen by nearly 60% from their peak levels. Argus states that this bifurcation reflects structural changes that have permanently altered the market's pricing structure. The primary driver of this bifurcation is China's export controls, implemented in February 2025. China accounted for approximately 83% of the world's mined tungsten in 2024, yet export controls have significantly constrained global availability, creating tight prompt supply outside China and supporting firm European prices while domestic Chinese competition intensifies. Supply dynamics within China are also shifting. Recycled tungsten is expected to account for around 35% of China's total tungsten supply, up from approximately 25% in 2024-25. This expanding scrap supply has created price pressure domestically, particularly in lower-grade materials, while also reducing Chinese exporters' ability to supply global markets. The Argus study also analysed the current market to assess the selection of the production of tungsten concentrate versus production of APT (the intermediate product). The conclusion was that, given the current market situation with tightness principally in the supply of concentrate (particularly with China importing increasing quantities of concentrate), production of tungsten concentrate would be preferable. This conclusion was reached purely on the assessment of market conditions rather than any project economic considerations. Project Overview The Sisson Project is owned by the Sisson Limited Partnership in which Northcliff owns an 88.5% interest and Todd Sisson (NZ) Limited, a subsidiary of Todd Corporation of New Zealand owns an 11.5% interest. A positive Feasibility Study based on a nominal 30,000 t/d open pit mine and processing facility with an APT plant was completed in 2013, and the Sisson Project entered the provincial and federal Environmental Impact Assessment ("EIA") process later that year. Provincial and federal EIA approvals were received in 2015 and 2017, respectively, followed by other key approvals, including a Metal and Diamond Mining Effluent Regulation Schedule 2 amendment authorization in July 2019 and a Fisheries Act Authorization and an Off-setting/Fish Habitat Compensation Plan Authorization in October 2020. More recently, Northcliff advanced work toward meeting the conditions associated with its EIA approvals and initiated the Feasibility Study Update and other activities to progress the Sisson Project through the pre-construction phase. Located 100 km by road northwest of Fredericton, New Brunswick, access to the Sisson property is gained via paved highway and good quality gravel forestry roads. Forestry roads also provide access to most areas of the property. The deep-sea port at Saint John is accessible by road from the site. All necessary supplies and commercial services for exploration and mining can be acquired in Fredericton. Daily international commercial air service operates out of Fredericton, as well as rail, bus, courier, and truck transport. Several towns and villages located in the Project area can provide labour and additional support services. Mine and Infrastructure The proposed Sisson mine site will include an open pit, process plant and tailings storage facilities, water treatment plant and ancillary buildings. The latter include offices, shops, warehouses, transportation, communications and power supply and distribution infrastructure (Figure 1). The Project will be accessed using a combination of existing public and forestry roads and Project-specific access roads. Existing road corridors will be used to the greatest practical extent to reduce new disturbance, earthworks, environmental effects, and capital cost. Upgrades will generally be concentrated at locations where the existing road geometry, pavement structure, drainage, visibility, or structural condition does not satisfy the anticipated construction and operational traffic requirements. Existing bridges along the access routes were previously established for single-lane forestry traffic, including logging vehicles with a gross vehicle weight of up to approximately 62,500 kg. The condition and load capacity of these structures will be confirmed through structural assessment before they are relied upon for Project construction and operational traffic. Traffic-control measures will be implemented where continued public, forestry, or Project access must be maintained during construction. The Project's power requirements will be satisfied by utilizing the existing New Brunswick electrical grid. Approximately 9 km of the existing 345 kV transmission line that crosses the Sisson claims will be relocated away from the Project facilities. A new 42 km 138 kV power line will also be constructed by NB Power from the existing line to the facilities and there will be upgrades to the Keswick Terminal, providing the Project with 58 MW of power.
Mine Operations The Sisson Project will utilize conventional, owner-operated open pit mining methods utilizing a truck-and-shovel fleet. The operation is designed for year-round production at a nominal mill feed rate of 30,000 t/d or 10.5 Mt/a. The mining fleet has been selected and optimized to support mill feed requirements while providing flexibility for ore, barren rock, and quarrying activities. The operation will utilize Autonomous Haul Systems (AHS) to improve safety, increase hauling efficiency, reduce operating and personnel costs, and incorporate proven autonomous mining technology. The fleet will include hydraulic excavators, electric shovels, and front-end loaders matched with autonomous off-highway haul trucks. Key metrics of the Life of Mine Production are shown in Figure 2.
Metallurgy and Process Plant The process design is based on historical testwork and a recent testing program, both undertaken by SGS Canada using composites and variability samples from within the planned open pit. The overall design reflects industry standard equipment selection, robust operability, and maintainability considerations suitable for a large scale, long life open pit operation with an average nominal throughput of 30,000 t/d. Process water will be primarily sourced from thickener overflow streams and reclaim water from the TSF, maximizing process water recycling. Mineral processing will consist of crushing, grinding, and flotation flowsheet to produce separate molybdenum and tungsten concentrates. The comminution section of the selected flowsheet incorporates a three-stage crushing circuit and a single line ball mill grinding circuit operating in closed circuit with a cyclone cluster. Primary cyclone overflow will feed a series of flotation circuits designed to recover molybdenum first, followed by bulk sulphides, and finally tungsten. Transportation planning considers average production of 10,000 t/a of tungsten concentrate, and almost 4,000 t/a of molybdenum concentrate with peak years close to 7,000 t. Targeted off taking destinations will be smelters in the US, with a subset of concentrate tonnages, up to 1,000 t/a of tungsten and up to 5,000 t/a of molybdenum that may be diverted to European facilities. Concentrates will be trucked directly to smelters or loaded into sea containers directly at the mine and transported by truck to Port Saint John, New Brunswick for European destinations. Tailings and Water Management The tailing storage facility ("TSF") is located adjacent to the process plant area and open pit (Figure 1). Since the 2013 Sisson Feasibility Study, the TSF has undergone a significant design review to reflect updated tailings guidance, industry practice, tailings incident learnings, and additional EIA conditions. The TSF dam was reclassified to the highest rating under updated Canadian Dam Association guidance, resulting in a full centre-line design and a higher Inflow Design Flood. The water management system was also redesigned, including the addition of a tailings thickener to reduce water transported to the TSF and operational spillways to provide additional water management protection. The TSF will be constructed in stages using primarily quarried material from the Project site and will provide tailings and water storage capacity throughout the mine life. All mine rock and process plant tailings will be stored within the facility, with some barren rock diverted back into the open pit in the later years of mining to prepare for closure. The mid-grade stockpile will also be stored in the TSF. The TSF will also serve as the Project's primary water management facility, with contact water collected and treated and non-contact water diverted around mine facilities where practicable. Groundwater monitoring wells will be installed around the TSF to monitor seepage and water quality. A centralized WTP, located on the north side of the Process Plant will treat collected water to applicable federal and provincial requirements. Treated water will be reused within the Project where practicable, with surplus water discharged to the environment. The WTP will operate during the mine life and, as required, during post-closure active care. Environment and Closure Following the completion of mining, decommissioning, reclamation and closure of the Project will be undertaken to establish physical, chemical and biological stability of the site to the extent practicable, and to meet desired end land uses, all as required under provincial and federal legislation and regulations. All facilities, buildings and other infrastructures will be removed and the sites reclaimed except for those that will be used for ongoing care and maintenance of the site. The water management system will be reconfigured as needed to support the long-term stability of the site. The TSF embankments and beaches will be capped and re-vegetated, and a spillway will discharge to the open pit. Once the pit fills, water will be treated if necessary to meet regulatory requirements and discharged. Financial security is required by the Province to ensure acceptable closure of the Project. The amount of the required security will grow over the life of the mine to an estimated value of $210 M at closure in Year 27 in today's dollars. This reclamation bond funds closure and reclamation costs and post-closure water treatment costs in perpetuity. The estimated closure costs are based on a conceptual level closure and reclamation plan developed for the Feasibility Study Update. The closure concept is based on assumptions pertaining to water treatment requirements, soil replacement and revegetation details, and desired land end-uses. Economic Benefits During operation, the Sisson Project will directly employ approximately 300 people and approximately 500 during the construction phase. The project workforce will be drawn from surrounding towns and cities; no permanent work camp will be required. The Project is also forecast to generate $19,896 M in cash flow (post-tax) and $14,499 M in taxes and royalties would be paid over the 27 year mine life. Construction and operation of the mine would also require a variety of goods and services, many of which are described in the 2026 Study. With the results of the Feasibility Study Update in-hand, the Company intends to commission an Economic Study to provide additional information on the potential for increased economic activity locally, provincially and nationally. "I look forward to continuing Northcliff's dialogue with businesses and communities, including further discussions on capabilities to support the Project's progress from a supply chain perspective, as well as developing a strategy for specialized training where needed to build on existing skills and services in the local region and New Brunswick to support the proposed mine," said Northcliff CEO Andrew Ing. Community and First Nations Engagement Northcliff has engaged with local communities since it became involved with the Project and established a strong record of consultation during the EIA process. The Company is collaborating with New Brunswick based firms to assist with ongoing communications designed to meaningfully share project information with communities and First Nations. Since receiving the EIA approvals, Northcliff has continued to engage with the Wolastoqey in New Brunswick, in particular Wotstak (Woodstock) First Nation with which Northcliff has had a Co-Operation Agreement since 2017. The Province of New Brunswick also signed an Accommodation Agreement in 2017 with the Wolastoqey in New Brunswick ("Wolastoqey") relating to the Project. Northcliff continues to collaborate with the Wolastoqey Nation of New Brunswick ("WNNB"), the technical advisor to the Wolastoqey, by sharing information relating to the Project. The WNNB has participated in certain field activities of interest and Northcliff continues to seek their participation in upcoming field programs. The Company has also implemented additional engagement to include communication protocols issued in December 2025 by the Province of New Brunswick which expands its current engagement scope with the Wolastoqey to now include the consultative bodies for the Mi'mawe'l Tplu'tagnn Incorporated (MTI), Kopit Lodge and Peskotomukhati Nation and to all First Nation communities in New Brunswick to ensure a transparent, open and inclusive engagement process. Future Opportunities and Next Steps The 2026 Feasibility Study Update entailed a comprehensive review and verification of previous work, updates to reflect current economic conditions, as well as consideration and assessment of new approaches to optimize the mine development including updates and refinements to the TSF, water collection and treatment facilities, and integration of autonomous haul trucks and electric shovels in the open pit. Other opportunities will be further assessed as the project advances. "With the positive results from the Feasibility Study Update for the proposed mine at Sisson, we are planning for the basic engineering phase to optimize equipment selection, layouts and design criteria. We will continue to advance work to meet the conditions for the in-hand EIA approvals and additional requirements associated with the EIA extensions. During this next phase, the Company also plans to arrange financing for construction work and long lead orders for mining equipment in preparation for a construction decision in the latter part of 2027," said Mr. Ing. "Operations are expected to start in 2030." Feasibility Project Management and Contributions The Sisson Project Feasibility Study Update was led by Ausenco Engineering Canada ULC with input from consultants, specialists, and independent "Qualified Persons" for the purposes of National Instrument 43-101, who have reviewed the scientific and technical information in this release related to the 2026 Study.
The Company will file an NI 43-101 technical report on SEDAR+ within 45 days of this release. The technical report will contain project details and supporting information not included in this news release. All other scientific and technical information in this news release was reviewed and approved by Tanya Yang, P.Eng, a qualified person who is not independent of Northcliff. About Northcliff Resources Ltd. and the Sisson Project Northcliff is a mineral resource company focused on advancing the Sisson Tungsten-Molybdenum Project located in New Brunswick, Canada, to production. Additional information on Northcliff is available on the website at www.northcliffresources.com. Investor services can be reached at (604) 684-6365 or within North America at 1-800-667-2114. Andrew Ing Forward-Looking Information This document contains "forward-looking statements" that are based on Northcliff's expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should" and similar expressions. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These include but are not limited to:
Although such statements are based on management's reasonable assumptions at the date such statements are made, there can be no assurance that such forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such forward-looking information. Accordingly, readers should not place undue reliance on forward-looking information. Northcliff assumes no responsibility to update or revise forward-looking information to reflect new events or circumstances unless required by applicable law. For additional information regarding forward-looking statements and their related risks, please refer to the "Risk Factors" section in the Annual Information Form of the Company for the year ended on October 31, 2025, which is available on the Company's SEDAR+ profile at www.sedarplus.ca.
SOURCE Northcliff Resources Ltd. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Company Codes: Toronto:NCF | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||















